Eiterfeld school


Anlage Eiterfeld Mikrogasturbine

3 x CR65 gas microturbines

The energy balance of the biogas plant installed in Eiterfeld is improved because the three microturbines are directly installed in the consumer's basement boiler room. The 2.1 kilometre-long biogas pipe system delivers enough heat to supply the Lichtberg school and two kindergartens.

The project was planned and built by Greenvironment GmbH.

Technical data

Installed power:
195 kWel + 330 kWth

Fuel:
Biogas (renewable products)

Fuel consumption:
125 m3/h with 53% methane
660 kW RTI (rated thermal input)

Commissioned:
November 2008

NEWS:
2. - 4. Februar 2010
19. Jahrestagung Fachverband Biogas, Congress Center Leipzig




9. - 11. Februar 2010
E-world energy & water 2010,             Messe Essen

 

 

 

 

 

 

 

 

 

 

 

Deutsch


mikrogasturbine technologie