Biogas plant Ronnenberg
The generated electrical power of 200 kW is fed into the public supply network. The generated thermal energy is used to heat the fermenter.
The raw biogas produced is processed in a biomethane plant to natural gas quality. The resulting stripping unit is burned in the CHP plant to reduce the existing methane slip.
Specification
Electrical Power Output:
200 kW
Thermal Power Output:
150 kW
Fuel:
Biogas
Commissioning:
December 2010
Hot water, 200 kWel, Biogas, Germany